Sequence

Event/Task

Responsible Party

Comment

Time

Week 1

· Attend Account Set-up Call and complete brief set-up form. 

· Appoint a WorkRecords Manager and Compliance Manager

Property Contact or

Property WorkRecords Manager

WorkRecords will provide an Excel checklist that will be the basis for the call. 

30 min.

Week 1

· Coordinate internet connectivity and QR Code placement

WorkRecords Manager

High priority, completed by an IT/Engineering   contact as soon as possible

20 min.

Week 1

· Establish a GoLive date

· Transmit Supplier Notification Letters

WorkRecords Manager

The notification is a standard format draft provided by WorkRecords, transmitted to the suppliers immediately after the GoLive date is established

10 min.

Week 2

· Coordinate Orientation Call via the web for all internal users

WorkRecords Manager

A single web session for all internal users scheduled for the week Prior to GoLive

20 min.

Week 2

· GoLive

· Monitor worker’s activity at the QR Code

Buyer and Supplier Management

Ensure workers have the knowledge and understanding

10 min. per cycle

Week 3

· Complete department specific Labor-Buyer Training

Department Managers

Using Contract Staffing

Scheduled for the first week after GoLive and applicable to all software end-users

60 min. sessions

Weeks 3-6

· Monitor use of WorkRecords and provide feedback aimed at optimization and accuracy

WorkRecords Manager and

Compliance Manager

Monitoring use during the first 30 days serves to establish good habits that save time and money

2 min. per day